Timescale in Microsoft Project 2013

Paul O ConnorMember for 20 years 1 month
Created
1
5
0

Hi, when I want to show the week numbers on a construction programme in MSP 2013, the "Week 1" always go back to the start of the earliest activity, however I want to show pre-start activities i.e lead in activities before "Week 1" starts and don't seem to have a solution. I could do this very easily in MSP 2010!!!! Can anyone assist?? Thanks  - Paul

1 reply

Oldest first
  1. 0
    Ron Beechey ·

    I handled this issue by

    I handled this issue by setting the project start date to week one of the year in the case of 2015 I selected Jan 4.  That week became week 1 and I was looking for my project to start week 22 so I set the start milestone to this date and the weeks read correctly on a gantt chart print out.