Timescale in Microsoft Project 2013
In the Open Standard
Paul O ConnorMember for 20 years 1 month
- Created
- 1
- 5
0
Hi, when I want to show the week numbers on a construction programme in MSP 2013, the "Week 1" always go back to the start of the earliest activity, however I want to show pre-start activities i.e lead in activities before "Week 1" starts and don't seem to have a solution. I could do this very easily in MSP 2010!!!! Can anyone assist?? Thanks - Paul