Hi All,

 

In MS Project is it possible to remove the link between percentage complete and remaining durations.

the concern is that based on the assigned emaining duration the achieved/inserted % progress is changing. MS Project is calculating the progress based on duration only.

Thanks

Kannan

3 replies

Oldest first
  1. 0
    Tom Boyle ·

    I think you have understood

    I think you have understood correctly.  "MS Project is calculating the progress based on duration only."  In MSP,  "% Complete" is always the ratio (Actual Duration)/(Duration), where (Actual Duration) = (Duration - Remaining Duration).  You can't change this.

    So if you work for 5 days on a task with Duration=10 days, %Complete = 50%.  But if you work another 2 days before realizing that you have underestimated the time required to do the work by a factor of 2, now you have worked 7 days and have 13 days remaining; your %Complete is therefore 7/20=35%.  Backward progress!

    If you are serious about using MSP for earned value reporting, then you should be using Physical %Complete, not %Complete.  Or better yet, measure and report earned value progress using other tools.

    Good luck, tom

  2. 0
    Jose Frade ·

    Another hint:Change activty

    Another hint:

    Change activty type to fixed work.

     

    In field Work put your relative weight for all activities (Depending on project type: M/H, etc)

    Input progress of activities in field % Work Progress (Don't use activity % )

     

    Then your duration does not anymore depend on %

     

    Hope it helps

    JMFrade

  3. 0
    Kannan CP ·

    Tom and Jose,Thanks a lot

     

    Tom and Jose,

    Thanks a lot