Progress Calculation
In the Open Standard
Kannan CPMember for 18 years 4 months
- Created
- 3
- 2
0
Hi All,
In MS Project is it possible to remove the link between percentage complete and remaining durations.
the concern is that based on the assigned emaining duration the achieved/inserted % progress is changing. MS Project is calculating the progress based on duration only.
Thanks
Kannan
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?