Export MS Visio 2010 to MS Project 2010
- Created
- 0
- 3
I am trying either import an MS Visio File into MS Project or export an MS Visio File into MS Project. The instructions are pretty straight forward in Visio for exporting a file from Visio and the instructions read as follows:
-
On the Timeline tab, click Export Data.
Note When you export an expanded timeline that includes more data than appears on the original (such as additional milestones), you are asked if you want to export all of the data or only the data that is shared by all of the timelines.
- In the Export Timeline Data dialog box, navigate to the folder where you want to save the exported file. For File name, type the name you want to use for your Project file, and then click Save.
A confirmation message appears when the export is completed.
The problem is I don't see a "Timeline" tab in Vision. I did add a Timeline function, but it only does an import from other format into Visio. Can someone tell me either how to insert the Timeline Button in Visio so I can get to the "Export Data" option or perhaps point me in the direction of importing the file into Project through Project?
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?