Microsoft Project 2013 - Hierarchy Heading
In the Open Standard
Ivan SwanepoelMember for 10 years 1 month
- Created
- 1
- 3
0
Hi, I am a new member here, so please excuse if my first attempt at posting a question doesn't look right. Basicaly my question relates to Microsoft Project 2013. I have recently done a construction work programme, but my frustration is that when I filter tasks to show me tasks on only certain dates, it shows those tasks, but I need the group heading, i.e. the group name or heading, that this task falsl under to also show. Hopefully I've made my query clear becuase this is somethign that I have been battling forever with.