How to calculate expected finish date in MS Project ?

Karthik abiMember for 10 years 1 month
Created
2
6
0
Task nameBASELINE STARTBASELINE FINISHACTUAL STARTACTUAL FINISHEXPECTED COMPLETION DATE
Initial01-Aug05-Aug01-Aug05-AugNA
Task208-Aug10-Aug08-Aug12-AugNA
Task311-Aug12-AugNANA16-Aug
Task415-Aug17-AugNANA19-Aug
Final18-Aug19-AugNANA23-Aug

Task-2 exceeded 2 days, so final task is expected to be complete on 23-Aug as shown above.

How to calculate automatically the expected completion date when the actual finish date is different from baseline finish ?

2 replies

Oldest first
  1. 0
    Philip Day ·

    Karthik abi, If you have

    Karthik abi,

     

    If you have linked your tasks, MSP will complete this by operating a Forwards Pass. and the final task will automatically finish on the calculated Expected Completion Date. Be sure to Auto-Schedule your tasks to achieve this.

    You can check the scheduling method used on your project in the "Status" column:

    Image result for msp auto schedule icon

     

    You can check that the Forwards Pass is going to work correctly by checking the links in the "Precedessors" Column.

     

    I hope this helps, come back to us if you need any further help.

     

    Phil

  2. 0
    Philip Day ·

    oops posted twice, ignore!

    oops posted twice, ignore!

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?