Updating schedule with no progress

Moutaz AldeibMember for 22 years 9 months
Created
4
2
0

Hi Planners,

If I am updating my schedule on monthly basis and in a particular month there is no progress at all, how can I update it to show the slippage in dates for the critical activities "completion date of the project?

Is this related to the status date of the project which I changed but the dates did not.

Regards,

Muataz

4 replies

Oldest first
  1. 0
    Philip Day ·

    Hi Moataz, Are you taking

    Hi Moataz,

     

    Are you taking about Splitting your task which should have, but in fact did not have any work done to it?

     

    Phil

  2. 0
    Tom Boyle ·

    Muataz,Unlike other tools,

    Muataz,

    Unlike other tools, MSP requires you to explicitly re-schedule any slipped/delayed incomplete work as part of each update.

    There are a number of steps you should take before setting a new status date (including entering all your actual starts and finishes and confirming remaining durations of in-progress work.)

    After setting the new Status Date,

    1. Select the specific tasks that should have had progress but did not have any.  (If you have chains of logically connected tasks that should have been done, only select the first task in each chain.)
    2. Click "Update Project" on the Project ribbon.
    3. Choose "Reschedule uncompleted work to start after:" (Your new status date should be shown.  If not, change it.)
    4. Choose "Selected Tasks" - THIS IS MOST IMPORTANT and is not the default selection.
    5. Click OK.

    For unstarted tasks, this will impose a new early-start constraint on the Status Date.  For in-progress tasks, this will split the task at the end of its actual duration and resume it on the new Status Date.

    Notes: Any unstarted task with a non-SNET constraint will NOT be rescheduled - you'll have to revise the constraint yourself.  Also, any in-progress task will be split to satisfy delayed predecessors (unless you have unchecked the "Split In-Progress Tasks" scheduling option.)

     

    Good luck, tom 

  3. 0
    Ahmed Abdessalem, PMP ·

    Ms project will not di the

    Ms project will not di the calculatuin. You will have to do it yourself.

    Best Regards,

    Ahmed Abdessalem,

    www.drinac.com

  4. 0
    Mike Testro ·

    Hi MoatazJust enter the same

    Hi Moataz

    Just enter the same progress for the prevvious month.

    Best regards

    Mike Testro

Log in or join to reply