Progress
In the Open Standard
Moutaz AldeibMember for 22 years 9 months
- Created
- 7
- 3
0
Hi Planners,
Suppose I have 4 days duration activity and the status date is at the end of the second day, the % complete is 75%, this means that only one day remaining which is clear but the bar does not reflect this because the % complete is linked to the actual duration.
How to sort out this and make the actual duration two days and remaining 1 day (in total 3 days)?
Regards,
Muataz
7 replies
Oldest firstLog in or join to reply