Skip to content

MS Project 2007

Sabaapathy Selvamani BalasubramanianMember for 14 years 3 months
Created
5
2
0

Hi guys 

Is anybody can guide me, my project start  date & finish date is matching but the duration is not calculating properly , for eg. start date : 20-dec'16, finish date - 19-apr'18 , Duration should come - 474 days, BUT IT IS SHOWING ONLY 453 DAYS. 

When i check by changing the date format to hours format in Start date , it is showing different timings. But when i set initially the calendar i make standard time & working hours. If each activity hours is different then i need to change in each activity , like 20-dec'16 8:00 AM , finish date 19-Apr'18 17:00 PM.

Can anyone guide me ???? Urgent 

 

5 replies

Oldest first
  1. 0
    Tom Boyle ·

    Sabaapathy,MSP is calculating

    Sabaapathy,

    MSP is calculating the duration of the summary task exactly as the interval between its start and finish:

    • subject to the applicable task- or project- calendar; and
    • In working minutes (converted to "days" using the project's single "hours per day setting" in the schedule options).

    There are 485 solar days (+4 hours) between your start and finish milestones, and your expection of a 474-day project duration implies that you have accounted for 11.5 days of non-work exceptions, e.g. holidays (starting from a 7dx8h base calendar).  The 453-day computed duration implies that the actual assigned calendar for this summary task has an additional 21 days of non-working time over the 69-week duration of the project.  You need to find these in your calendar specifications.  For example, if standard work weeks include only 6 working hours on Saturdays, that could add an additional 17.25 days of non-working time.

    These issues are essentially the same for P6.

  2. 0
    Alexandre Faulx-Briole ·

    Hello,I suspect that

    Hello,

    I suspect that assigning a specific calendar to every task has also some consequences on MS Project calculating the project duration.

    When the Task Informations, Advanced, Calendar is displaying "None", that means that the task is being scheduled as per the project calendar; therefore, it is unnecessary to assign the "Standard" calendar to the task.

    Alexandre

  3. 0
    Sabaapathy Selvamani Balasubramanian ·

    Hi tom, Thanks for your

    Hi tom, 

    Thanks for your reply.

    Ya i agree , i have assigned some holidays for this specific project. If i make the " Task calendar " - select as None , Will i get the exact duration.

    When i calculate manually , i agree that i am gettting 486 days of the above project - Starts - 20-dec-16 to 19-apr-18.

    So what best i can do to change this overall duration as 486 days, bcos my manager is asking why the overall duration is less.

  4. 0
    Sabaapathy Selvamani Balasubramanian ·

    Hi tom, Thanks for your

    Hi tom, 

    Thanks for your reply.

    Ya i agree , i have assigned some holidays for this specific project. If i make the " Task calendar " - select as None , Will i get the exact duration.

    When i calculate manually , i agree that i am gettting 486 days of the above project - Starts - 20-dec-16 to 19-apr-18.

    So what best i can do to change this overall duration as 486 days, bcos my manager is asking why the overall duration is less.

  5. 0
    Tom Boyle ·

    As in all CPM tools, Duration

    As in all CPM tools, Duration in MSP is in Working Time, not solar time.  In my opinion your focus should be on understanding and explaining the basis for the 32.5 non-working days in your schedule.

    Follow Alexandre's advice and remove all the task calendars.  Assign a Project Calendar that properly reflects the working time you expect.

    If your "manager" fails to understand this and continues to insist on the durations in solar time, you may try to satisfy him by applying a solar-time task calendar (i.e. 7dx8h with no exceptions, with "hours per day" set to 8) to the summary task ID 1 only.  That's a step down a slippery slope, though.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?