MS Project 2007
- Created
- 5
- 2
Hi guys
Is anybody can guide me, my project start date & finish date is matching but the duration is not calculating properly , for eg. start date : 20-dec'16, finish date - 19-apr'18 , Duration should come - 474 days, BUT IT IS SHOWING ONLY 453 DAYS.
When i check by changing the date format to hours format in Start date , it is showing different timings. But when i set initially the calendar i make standard time & working hours. If each activity hours is different then i need to change in each activity , like 20-dec'16 8:00 AM , finish date 19-Apr'18 17:00 PM.
Can anyone guide me ???? Urgent
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?