Fixed Salary for the team of the project

Moutaz AldeibMember for 22 years 9 months
Created
0
3
0

Hi Planners,

I have a baseline schedule and I am filling the resources in the resource sheet but I faced an obstacles that I have human resources "Project Manager" that is working on the project since starting until closing out with a fixed salary, how to assign that resourcce to the tasks of the project?

If I assign that resource to all tasks of the project, the cost will be huge.

Regards,

Muataz

Replies

Oldest first

No replies yet. Be the first to answer.