Project with several phases of completion dates
In the Open Standard
Lo GaryMember for 16 years 8 months
- Created
- 7
- 3
0
Dear,
I have a project with 6 phases each has different contractual completion dates and liquidated damages. But all phases are inter-related. I consider they should have their own critical path.
It means the programme should have 6 critical paths.
What should I do?
I use subprojects to link them together in a separate project then it will show 6 critical paths?
Regards,
Gary Lo
7 replies
Oldest firstLog in or join to reply