Microsoft Project Updating - 2 Weeks Only
In the Open Standard
Shane KellyMember for 8 years 7 months
- Created
- 3
- 3
0
Hi All,
My boss has asked me to provide an update of project porgress for a 2 week timeframe only. This would range from the status date + 2 weeks. When using the 'date range' filter it shows activities that start in this timeframe and finish after it. Is it possible to create a filter to show work complete only in this timeframe. An activity that finishes after this could be 100% complete only within this timeframe but not 100% complete in real terms. Any help or advice would be greatly appreciated?
Kind Regards
S.K
3 replies
Oldest firstLog in or join to reply