Skip to content

Microsoft Project Updating - 2 Weeks Only

Shane KellyMember for 8 years 7 months
Created
3
3
0

Hi All, 

My boss has asked me to provide an update of project porgress for a 2 week timeframe only. This would range from the status date + 2 weeks. When using the 'date range' filter it shows activities that start in this timeframe and finish after it. Is it possible to create a filter to show work complete only in this timeframe. An activity that finishes after this could be 100% complete only within this timeframe but not 100% complete in real terms. Any help or advice would be greatly appreciated? 

Kind Regards

S.K

3 replies

Oldest first
  1. 0
    Trevor Rabey ·

    finish_date_filter.jpg

  2. 0
    Trevor Rabey ·

    finish_date_filter.jpg

  3. 0
    Prial Handig ·

    Hi Shane,One way to do that

    Hi Shane,

    One way to do that is to set a baseline of your project and create a filter:

    Field Name: "Baseline Finish"

    Test: "is less than or equal to"

    Value: input the date two weeks ahead from your status date (i.e., if the date today is 2 May '18, then input "16 May '18")

    That will show you all the activities that should be completed before and on 16 May '18.

     

    Hope this helps.

    Regards,

    PH

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?