MS Project- Progress Line
In the Open Standard
Alan BoultonMember for 7 years 10 months
- Created
- 2
- 2
0
Hi
I have an issue with the progress line in MS Project.
I have a summary bar that has all the sub tasks beneath it with 0% complete. The summarry bar also shows 0% complete, but when the progress line is added to the Gnatt chart it shows all the sub tasks correctly, but the summary task is showing as 100% complete.
Any help greatly appreciated.
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?