How to link Percent Complete to Progress Periods
In the Open Standard
Cameron IllingworthMember for 5 years 8 months
- Created
- 1
- 3
0
Good morning everyone,
I would like to link the Percent Complete to the Progress Period so that when I am looking at each Progress Period, the Percent Complete entered will reflect that Progress Period. This relationship is present with the Progress Period dropline, so that if I display ultiple Progress Period droplines, they reflect the percentages I entered for the period. But once I enter progress into Percent Complete, this value in the spreadsheet doesn't change when alternating between Progress Periods.
Is there anyway to do this?
Many thanks,
Cameron