How to link Percent Complete to Progress Periods

Cameron IllingworthMember for 5 years 8 months
Created
1
3
0

Good morning everyone,

I would like to link the Percent Complete to the Progress Period so that when I am looking at each Progress Period, the Percent Complete entered will reflect that Progress Period. This relationship is present with the Progress Period dropline, so that if I display ultiple Progress Period droplines, they reflect the percentages I entered for the period. But once I enter progress into Percent Complete, this value in the spreadsheet doesn't change when alternating between Progress Periods.

 

Is there anyway to do this?

 

Many thanks,

Cameron

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Hi Cameron,there is no such

    Hi Cameron,

    there is no such Progress Period in MSP as in Primavera P6;

    the Progress Line does not store the corresponding data in a field available to the user; therefore, as far as I know, you should use a numeric custom field to key in the Period Performance every time you display a Progress Line

    a time consuming process if I can say, and MS Excel would be a more appropriate tool for that

    Alexandre