MS Project 2016 - Renumber wbs of selected task is greyed out in MS project

Pranab Kumar DebMember for 19 years 8 months
Created
1
3
0

Hi All, 

 

I am using MS Project 2016 and want to renumber a selection of activities but the renumber wbs selected task in ms project 2016 is greyed out.  I have tried the task sheet view and removing the autofilter, nothing works

 

Please help. 

 

regards

 

Pranab 

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Hi Pranab,you need to select

    Hi Pranab,

    you need to select several tasks together; when you select only one task, you can only renumber the whole project

    Alexandre

Log in or join to reply