Microsoft Project 2016:Convert or save a baseline into another
In the Open Standard
Pranab Kumar DebMember for 19 years 8 months
- Created
- 1
- 5
0
Hi All,
I have a project where all the 11 baseline allowed in MSP has been used, the problem is the "Baseline" is the last image of the schedule that the scheudler saved before the last update. "Baseline1" is March end and "baseline2" is February end, now I want to copy the "baseline10" to "baseline" as "baseline10" is the "real baseline" for the project at award.
Second question is, Is there a way to delete cost and work information from the baseline schedule before sending this to the client.
regards
Pranab
1 reply