How to schedule un -splittable tasks
In the Open Standard
Alexandre Faulx-BrioleMember for 23 years 8 months
- Created
- 7
- 6
0
Hello Planners,
one customer of mine is asking the fommowing question, I have to admit that I am not able to answer it; does anybody have an idea?
**************
My project takes place during Scheduled Machine Shutdowns (SMS).
Today when the different Tasks (T) / Group of Tasks (GT) exceed the duration available on the SMS,
they start on SMS(n) and end on SMS(n+1).
I would like to avoid this splitting and have
*if T-GT is not terminated on SMS(n) then starts in SMS(n+1)
i*f there is no automatic solution, I have to manually manage TWT (Non-Worked Task) to perform the shift and this is very tedious to create.
Moreover, if a task preceding the TWT is delayed, I have to rectify the TWT accordingly so that my schedule for the SMS is not all shifted.
Subsidiary question :
if the duration of T-GT > SMS' initial duration, how to have a way to visualize that I have to program an SMS longer than expected
*****************
"SMSs" are not tasks, but non-working periods in the calendar of a resource "SMS"
I know that Powerproject and Spider allow tasks to be "un-splitable"; I know that MS Project allows tasks not to be split during resource leveling; but I cannot find a way to answser my customer.
Thank you for your help,
Alexandre
P.S. I am sure Raphaël will have a bright idea!
7 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?