Productivity Tracking in P6

Mohammad Naeem AhmadMember for 16 years 3 months
Created
2
5
0

Good Evening Gents'

 

I'm trying to track my productivity through P6 along with quantity tracking. But while designing report i'm facing problem, how to call actual units per time , planned units per time & remaining units per time.  Coz these three columns can help me in calculatin my planned, actual and forecast productivity. So if anybody have any idea about this please help me out.

 

Regards

 

Naeem

2 replies

Oldest first
  1. 0
    Daniel Limson ·

    Hi Mohammad,In order to track

    Hi Mohammad,

    In order to track productivity you need the following:

    Plan Units per time - Budgeted Labour Units (Manhours or Mandays)

    Earned Value - based on physical progress % complete (Budget Labour Units * % complete)

    Actual Units per time - based on actual resources (manhours or mandays) this you need to input manually

    Now, Productivity = Output (Earned) / Actual

    Budgeted Labour Units - Progress Earned  = Remaining Units per time

    Budgeted at Completion (BAC) or Forecast at Completion = Remaining Units per time / Productivity

    Cheers mate,

    Daniel

  2. 0
    Aijaz Syed ·

    Hii GuysI need Productivity

    Hii Guys

    I need Productivity Template and Progress Managment Template or format to make one for my ongoing project.

    If possible please forward it to my e-mail my e-mail adress : syd.aijaz@gmail.com

    Thanks

    Aijaz Syed