Earned Value Tracker template

Nisha JosephMember for 9 years
Created
2
46
0

Hello,

 

I work in the Oil & Gas Engineering projects. The client has requested for a EVM tracker and Productivity reports. Can someone share a template and brief guideline, on how to calculate it.

 

Thanks for your efforts and time,

Nisha

2 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Show the Time Distributed

    Show the Time Distributed Planned Value and EV.

    The Productivity rate will be (Current EV - Previous EV) / Time Period Interval

  2. 0
    Nisha Joseph ·

    Well Noted. Thanks

    Well Noted. Thanks