Monte Carlo Risk Analysis

Hermie LaOMember for 21 years 8 months
Created
6
3
0

Correction! This is a methodology NOT a product!!!

Open has this built in as a scheduling functionality.

6 replies

Oldest first
  1. 0
    Sai Prasad ·
    Hi
    Please let me know what is this Monte Carlo Risk Anlysis & where do I get to learn this methodology
    regards
    sAI
  2. 0
    Hermie LaO ·
    Hi Sai,

    Basically, Monte Carlo Analysis allows you to enter Optemistic/Most Likely/Pessimistic durations on activities. You then identify the task you wish to evaluate(ie project/milestone completion activity).

    You then run iterations where the system computes different combinations using programme logic and duration combinations.

    End result would be a % likely completion of the identified milestones and completion dates.

    Regards,

    Hermi
  3. 0
    Bernard Ertl ·
    You can read about Monte Carlo Risk Analysis in Chris Hendrickson’s on-line book Project Management for Construction: Scheduling with Uncertain Durations

    There are several discussions in the Schedule Risk and Schedule Risk Analysis forum regarding Monte Carlo.

    Bernard Ertl
    eTaskMaker Project Planning Software
  4. 0
    Sai Prasad ·
    Thank Benard
  5. 0
    Ashraf Alawady ·
    Hi
    you can get the neccesary information by reading ’PMBOK’book (Project Management Body Of Knowledge)or visit the website of the project management institute at www.pmi.org.
    Good Luck
  6. 0
    Mehdi Rashidi Alangeh ·
    Open Plan was capable of quick Monte Carlo simulations, and gave detailed information regarding our activities’ early and late dates