I am a new user to OPP and I am having trouble working with an existing project. All the subproject activities have a start date equal to TimeNow and a finish date based on the latest finish date of the child activities.

Why is the early date for the subproject equal to time now and not the earlist start date of the applicable child activity?

5 replies

Oldest first
  1. 0
    Joanne Foster ·
    You need to go
    Project menu > Time Analysis
    then ensure that "Actual Date Option" and "Show Summary Dates in Subprojects" is selected (the later is the option will rollsup the dates correctly.

    Why on earth you wouldn’t want that happen, and thus make it an option is beyond this little black duck!

    J
  2. 0
    Oscar Wilde ·
    is open plan very popular in australia seems to be
    do you guys not use P3
    Have you seen bills comments about knuckheads
    Hermie
    Help
  3. 0
    Oscar Wilde ·
    ps whatsa black duck
    sounds intriguing (SP)
  4. 0
    Joanne Foster ·
    open plan is used mostly by defence, there are of course other users, but defence is probably the biggest user of open plan.

    P3 is used extensively in Oil & Gas, Mining, Construction etc.

    J
  5. 0
    Joanne Foster ·
    I don’t know enough about P3 to make a contribution to which is better, or which is better suited what industry.

    I used to be a huge fan of OPP, but since the release of v3 my confidence has gradually reduced to the point where I now have ZERO confidence in anything which Welcom produces.