Progress Display on bars

Rajeev KumarMember for 23 years 5 months
Created
4
4
0
Is there a way I can show the physical progress % on the bar?. I have a baseline schedule and I dont want to update it, but I just want to show the physical percent complete in some graphical way on the activity bar, either a shade or a line on top of the bar. Say for example, an activity of duration 10 days(from 1Jan06 to 10Jan06 is 30% complete, I just want to show a bar of 1Jan06 to 10Jan06, with shade or colour from 1Jan06 to 3Jan06, irrespective of whenever the start date was or remaining duration will be.

I know it sounds a bit weird, but my boss it needs it that way.

Thanks
Rajeev

4 replies

Oldest first
  1. 0
    Joanne Foster ·
    yes there is...but it involves creating calculated fields and is a bit complex to explain. Perhaps contact Welcom and see if they can provide you some information on it.

    Regards
    Joanne
  2. 0
    Rajeev Kumar ·
    Thanks Joanne,

    I figured it out using Calculated fields and barchart preferences. Some features are really amazing in OPP.

    Cheers
    Rajeev
  3. 0
    Syed Zaidi ·

    how can i show it? can you

    how can i show it? can you please tell me the steps?

  4. 0
    Raymund de Laza ·

    SZ, performance.jpg

    SZ,

Log in or join to reply