Airport Schedule

VenkataRao BodapatiMember for 19 years 11 months
Created
22
3
0

Can anyone share his eperience of Making Airport medium size Schedule.

22 replies

Oldest first
  1. 0
    Ponnaganti Sridhar ·
    Hi
    Hello Venkatarao.B which kind of Airport schedule you are looking for? Is that an international Airport or Domestic Airport?

    i Have a little Experince in AirportSchedule Pepration, i was there in Schedule perpration of Doha International Airport,

    so what are you looking for? is the Schedule of entire project or related to only some Utlity area??
  2. 0
    VenkataRao Bodapati ·
    asasa
  3. 0
    VenkataRao Bodapati ·
    Hai Sridhar,
    I need the complete schedule if you have otherwise whatever you have send it to my mail id
    bvenkatvg@yahoo.com
  4. 0
    Mohamed ElTantawy ·
    Dear Sir

    may i ask you to have a copy of this schedule on my mail meltantawy@yahoo.com

    I will be thankful for your kind help
  5. 0
    Salahuddin Ahmed ·
    Hi, Sridhar

    Could you please send me WBS and Acrivities of whole schedule of typical airport project.
    Thanks in advance
    salah.ahmed80@yahoo.ca
    Regards

    Salah
  6. 0
    Ashutosh Nema, PMP ·
    Dear
    Can u please send me this also.
    My Mail Id is ashutoshnema19@gmail.com
    Thanks
    Ashutosh Nema
  7. 0
    Arnold Puy ·
    Hi Sridhar,

    Can you send me also Please at p3-fer@sixco.ae

    Arnold
  8. 0
    Muhammad Yaseen, PMP ·
    Mr. Sridhar

    may i ask you to have a copy of Airport Schedule on my mail seanum89@gmail.com

    I will be thankful for this act of kind help
  9. 0
    Samer Zawaydeh ·
    Dear V,

    The best start would be to have the following General activities and then start expanding the details as per your Contract requirements.

    I) Infrastructure
    Civil - Cut and Fill, Base course, Asphalt, concreting
    Electrical - Power, Lighting, Low Current
    Mechanical - Plumbing, District Cooling

    II) Buildings
    regular activities + special designs.

    The special systems and requirements will have to be read from the drawings, specifications and BOQs.

    Best,

    Samer
  10. 0
    osama Eltantawy ·
    Mr. Sridhar

    may i ask you to have a copy of Airport Schedule on my mail usama022007@yahoo.com
    I will be thankful for your help

    Osama
  11. 0
    R. Catalan ·
    Hi Sridhar,

    Send me also a copy at planning_me@yahoo.com

    Many thanks,
    R. Catalan
  12. 0
    David Wallace ·
    Please remember when building your schedule that you remember more than just the civil/construction aspect.

    Airports are usually confined to specific codes and rules from various organisations from the local Civil Defence to an International Safety Body.

    You will need to consider Special and Specific Airport Systems, large PAX safety systems, boarding and customs gates, alarms and life safety, aircraft interaction, and the list goes on and on.

    If you are asking for the schedule, I’ll assume that you are working on an airport project, no doubt with a firm that has experience in this field. You should perform Front End Engineering Design Discussions with your M&E Managers, HS&E Teams, Design Management and Project Teams.

    If you are involved in a the construction of a specific section of the works, a hangar for example, you still need to consider the aircraft and airport interaction.

    When you have built your schedule, resourced & levelled it, make sure the constraints and logic are spot-on, I will be absolutely shocked if you do not get variation or change or are delayed by your client, so be prepared to impact your programme.

    This advice is from experience, I spent two years performing the Delay Analysis on a major Airport in the Middle East, and that was with a good planning team already in place for the Contractor.
  13. 0
    Se de Leon ·
    For airport project, always look for someone who has an experience with ORATT(Operational Readiness, Testing & Transfer). These people know excatly what to look for in an airport project schedule in order to make sure that the airport will open successfully and on schedule. The people I worked with before who does this kind of work has an extensive experience with ICAO, that’s why they are very knowlegeable about airport construction and regulations.

    No airport project has become successful just because the building is constructed. It will all boil down to the various airport systems and its integration. The heart of this is the Baggage Handling System. Remember chep lap kok?

    To make the long story short, make sure that the various airport systems have their realistic interface dates shown in the schedule from design to execution.

    My 2 cents.
  14. 0
    Marian Anyameluhor ·
    Please can I also have the info on airports sent to m_arafiena@hotmail.com

    Many thanks
  15. 0
    Sarfaraz M Nasim ·
    Dear
    Can u please send me this also.
    My Mail Id is sarfaraz.nasim@gmail.com
    Thanks
    nasim
  16. 0
    Nadeem Akram ·
    I Urgently need a Sample Programme Details of activities WBS Constraints every possible details of any Airport I got Interview and I have to show them a Samply Project please any one e-mail me asap regards


    Regards

    Nadeem Akram
    London UK

    nadeem.akram@hotmail.com
  17. 0
    Mohamed ElTantawy ·
    Mr. Sridhar

    may i ask you to have a copy of Airport Schedule on my mail meltantawy@yahoo.com

    I will be thankful for this act of kind help
  18. 0
    Julius Calantas ·
    Ponnaganti,

    Could you send to me also.

    julius2532@yahoo.com
  19. 0
    Mehmet Oguzalp ·

    I will be really happy if you

    I will be really happy if you send me a sample of airport construction  schedule also. mehmet_oguzalp@yahoo.com

  20. 0
    Mhd Matar ·

    may i ask you to have a copy

    may i ask you to have a copy of Airport Schedule on my mail eng.matar@hotmail.com

    I will be thankful for this act of kind help 

  21. 0
    Mhd Matar ·

    may i ask you to have a copy

    may i ask you to have a copy of Airport Schedule on my mail eng.matar@hotmail.com

    I will be thankful for this act of kind help 

  22. 0
    Gary Whitehead ·

    As far as I can tell ,no-one

    As far as I can tell ,no-one ever actually offered to email out a copy of an airport schedule in the first place.

     

    Thread locked.