OPP views dummied up to look MSProject-ish

Steve GrimmettMember for 19 years 9 months
Created
1
4
0
G’day folks,
Have a question that on the face of it looks bit on the numpty side. I have a situation where I need to make my schedule views (Gannt chart especially and possibly Network diagram also) look like MS Project (something about customer comfort with familiar product)output but I want to retain the schedule in OPP (’cos I’d still like to be able to plan and schedule using a real scheduling tool).
I seem to remember there was a view in OPP that made output appear MSProject-ish. Was I dreaming it or is there a canned view that has an MSProject Gannt chart presentation.

1 reply

Oldest first
  1. 0
    Joanne Foster ·
    It doesn’t come out of the box (as far as I know), but you can change the barsets and appearance of the spreadsheet to make it look a little more like MSP.

Log in or join to reply