Baseline help

Susan LaurensonMember for 21 years 9 months
Created
0
2
0
I have come across a problem today when re-baselining one of my plans, after re-baseling,activities that are in progress and have a remaining duration

example - 60% complete to time now
40% remaining

what is happening is that there are 256hrs remaining to end completion date 3months from time now, the baseline has calculated that 40/100x256/3months this is only given me approx 50% of the remaining resource hours and makes my forecast all out of sink

if someone has come across this, please help (-:

all my baseline data up to timenow is perfect
regards
Susan