Skip to content

CPI & SPI trend

Abbas RajabpourMember for 4 years
Created
1
3
0

Hi all, 

I've been asked to give a presentation of the SPI & CPI trend of a project based on the last 12 months update. Is there a way that I can assign each update's baseline and get the CPI & SPI? Not sure how to do that if we haven't captured each month in the reports.

1 reply

Oldest first
  1. 0
    David Kelly ·

    If you used the 'Store period

    If you used the 'Store period performance'facility after each progress update, then you have all the raw data (planned/earned/actual) to make the spreadsheet. If not, it is quite a job. You will need to restore each baseline, and extract each period's data into a spreadsheet.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?