Error Code PRMDB-0900-0
- Created
- 1
- 5
Dear Planners,
i'm using P6 version 24 Server , with 5 Users , every thing is ok, untill the user is leaving the P6 idle ( not used for 10 to 15 min, then when the user try to dop any filter or layout the below error showing up/
Event Code: Error Code PRMDB-0900-0.
Exception EPRM DBSQLexecution Failure Model PM.EXE at 000000000941B23B
PRMDB Access Error: Error Received Fro,
No DBAPI.Tansmitand receive : Orcake ORA-12571
Encountered
Below more details
*****************************************************
* EXCEPTION REPORT *
*****************************************************
Date: 03-Apr-25
Executable: PM.EXE
Application: Primavera P6 Professional 24
Event Code: PRMDB-0900-0
Message:
PRM DBAccess Error: Error executing query. Error:
Oracle error ORA-12571 encountered.
Time: 03-Apr-25 10:57:55
Context:
1: TDevxMainForm.actProjectActivitiesExecute
2: TDevxMainForm.BeforeFormShow
3: TDevxMainForm.actProjectWBSExecute
4:
5:
6:
7:
8:
9:
10:
Detail:
Type: EprmDBSQLExecutionFailure
Object Type: TPopupList
Database Error:
Error Code: 0
System Info
===========
Username: 20378723 Hostname: PLO20378723ADO
OS Version: Windows NT ver 6.2, build 9200, ((unknown))
About P6:
Any solution or suggestion to fix this issue ???
Regards,
Tarek
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?