Does P3e have "Continuous/Interruptible" CPM Setti
In the Open Standard
Ronald WinterMember for 23 years 9 months
- Created
- 1
- 3
0
I have looked everywhere (including in the Help file and the manual) for the P3 equivalent of the Continuous / Interruptible Activity setting when computing the CPM. To my knowledge, P3e seems to always use the "Continuous" setting whenever computing the CPM and you have a pair of unbalanced Start-To-Start and Finish-To-Finish relationships between two activities.
P3 would give you the option of stretching the duration of the successor to meet both constraints. This is called, "Interruptible." Does anyone out there know any more about this? Without equal settings, the same schedule may show different dates on different software platforms.
P3 would give you the option of stretching the duration of the successor to meet both constraints. This is called, "Interruptible." Does anyone out there know any more about this? Without equal settings, the same schedule may show different dates on different software platforms.
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?