Does P3e have "Continuous/Interruptible" CPM Setti

Ronald WinterMember for 23 years 9 months
Created
1
3
0
I have looked everywhere (including in the Help file and the manual) for the P3 equivalent of the Continuous / Interruptible Activity setting when computing the CPM. To my knowledge, P3e seems to always use the "Continuous" setting whenever computing the CPM and you have a pair of unbalanced Start-To-Start and Finish-To-Finish relationships between two activities.

P3 would give you the option of stretching the duration of the successor to meet both constraints. This is called, "Interruptible." Does anyone out there know any more about this? Without equal settings, the same schedule may show different dates on different software platforms.

1 reply

Oldest first
  1. 0
    Khalid Abdelaal ·
    Dear Ronald

    Schedule durations role (contigous or interruptible)is only included in P3 and doesnt included in P3e


    Khalid Abdelaal

Log in or join to reply