P3e - Resources and Durations
In the Open Standard
Dave McGinnisMember for 22 years 8 months
- Created
- 3
- 3
0
Hello all, New Guy here...
Is there a way to try a 2-shift option without changing each activity’s resource units to 200%?
I want to see how adding a night shift affects the schedule on some earthworks activities. I have assigned 1 scraper fleet (max units available 200%) to each of these activities. Unless I change the remaining units/time to 200% manually, the durations don’t change. Can I do this any easier? I have seen the "Shift Calendar" within the resource screen, but am unclear how this is used, or if this is the direction I should head.
Any thoughts?
Thanks,
Dave
Is there a way to try a 2-shift option without changing each activity’s resource units to 200%?
I want to see how adding a night shift affects the schedule on some earthworks activities. I have assigned 1 scraper fleet (max units available 200%) to each of these activities. Unless I change the remaining units/time to 200% manually, the durations don’t change. Can I do this any easier? I have seen the "Shift Calendar" within the resource screen, but am unclear how this is used, or if this is the direction I should head.
Any thoughts?
Thanks,
Dave
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?