P3e - Resources and Durations

Dave McGinnisMember for 22 years 9 months
Created
3
31
0
Hello all, New Guy here...

Is there a way to try a 2-shift option without changing each activity’s resource units to 200%?

I want to see how adding a night shift affects the schedule on some earthworks activities. I have assigned 1 scraper fleet (max units available 200%) to each of these activities. Unless I change the remaining units/time to 200% manually, the durations don’t change. Can I do this any easier? I have seen the "Shift Calendar" within the resource screen, but am unclear how this is used, or if this is the direction I should head.

Any thoughts?

Thanks,
Dave

3 replies

Oldest first
  1. 0
    Admin Team ·
    use "what if" project facility....
  2. 0
    Roberto Bustos ·
    For me, im not changing the availability to 200%. because it is for the max limit of a resource that you can use at the same time.

    if you want to have it 2 shifts, maybe it would be better if you check first if your planning unit is in "hours", then go to the calendar and change it to 2 shifts by specifying the time of work in the hours area. you just have to make a 2-8hrs shift. it depends on your no. of hours per shift.

    so regardless of your max. availability, your resource will now be forecasted or distributed in 2 shift calendar format.

    your duration however will still be depending on the units per time, because if your upt is within the limits per time period, then duration will not change, if it exceeds, then it should change.

    and also check your driving resource to make your duration depend on your upt.

    i dont know how others do this but this is how i do it. maybe there is still other way to do it easier and faster.
    hope you find this helpfull, good day!!!

  3. 0
    Admin Team ·