Driving Predecessors

Rafael DavilaMember for 22 years 7 months
Created
3
3
0
I have been a P3 user for some time, although new to P3e. In order to analyze schedules I need to know how does P3e marks driving predecessors. P3 marks them with a simple asterisk. P3e approach must be similar.

The new scheduler is new to P3e. My new computer is not set up with Metaframe yet, therefore P3e is not available in my computer. My duties as Project Manager does not allow me to sit for hours exploring P3e. Fortuantelly forums like this are available.

MS Project lack this essential feature, that’s why I consider MS Project a child’s play.

3 replies

Oldest first
  1. 0
    Forum Guest ·
    Thank’s this should do it, as soon as I get Metaframe set up in my computer I will work on it.

    Today I asked the scheduler for a very simple schedule, 24 activities, for a presentation but for some reason the dependancy arrows show incorrect relationships, do it ever happened to you. Is it a bug or our scheduler?

    R Davila
  2. 0
    Forum Guest ·
    Hi there,
    glad to be of assistance,
    That’s not a bug, you need to go into View>Bars, sounds as though the logic is showing on the baseline, not the current tasks....

    Important...In The view bars menu ( list of different types )...the LOWER the order in the menu screen the HIGHER the priority, so you’ll need to ensure that the current task bars / milestones ( including complete bars / critical bars / milestones are below the baseline bars / milestones..

    This should sort it !

    Regards,

    David Garside
  3. 0
    Forum Guest ·
    David, thank you very much, keep hanging around just in case we need your advise again.

    R. Davila

Log in or join to reply