Force to show critical task

Yusuke KamuiMember for 18 years 5 months
Created
4
1
0
Hi,
I’m using P6.2, I have a task named "INSTALL SCAFFOLDS" having a FREE FLOAT of 0 day and a TOTAL FLOAT of 30 days. It is not being shown as critical but I want to show it as as a critical task, how to force it to show as a critical task? I have other tasks having a FREE FLOAT of more than 0 days and a TOTAL FLOAT of 20 days but I don’t want them to show a critical, only the task named "INSTALL SCAFFOLDS".

Psl advise. Thanks!

4 replies

Oldest first
  1. 0
    Gary Whitehead ·
    why would you want to show it as critical when it isn’t?

    Free Float has nothing to do with criticality -it is only Total Float that defines the critical path.
  2. 0
    Anoon Iimos ·
    Yusuke,

    Though your schedule might not show it as critical, the activity ("install scaffold") is really necessary and practically critical (or is it not?).

    There are several ways to do it, but I supposed if you had arranged or organized your activities practically, for sure it will show as critical, please check the logic links.

    cheers

  3. 0
    Balaji Surendiran ·
    To make an activity critical either you need to play with the relationaships or apply contraints(not a right way of making a activity critical)...

    regards
    Balaji
  4. 0
    Neal Walsh ·
    Yusuke,

    F9, Options.....

    Make sure that under the ’Define Critical Activities’ it is set to 0 days, and not a negative figure, as this will eliminate Activities with 0 days Total Float from the Critical Path.

    Walshy