Force to show critical task
In the Open Standard
Yusuke KamuiMember for 18 years 5 months
- Created
- 4
- 1
0
Hi,
I’m using P6.2, I have a task named "INSTALL SCAFFOLDS" having a FREE FLOAT of 0 day and a TOTAL FLOAT of 30 days. It is not being shown as critical but I want to show it as as a critical task, how to force it to show as a critical task? I have other tasks having a FREE FLOAT of more than 0 days and a TOTAL FLOAT of 20 days but I don’t want them to show a critical, only the task named "INSTALL SCAFFOLDS".
Psl advise. Thanks!
I’m using P6.2, I have a task named "INSTALL SCAFFOLDS" having a FREE FLOAT of 0 day and a TOTAL FLOAT of 30 days. It is not being shown as critical but I want to show it as as a critical task, how to force it to show as a critical task? I have other tasks having a FREE FLOAT of more than 0 days and a TOTAL FLOAT of 20 days but I don’t want them to show a critical, only the task named "INSTALL SCAFFOLDS".
Psl advise. Thanks!
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?