Skip to content

No Baseline for Level of Effort Tasks

Robert AdamsMember for 22 years 1 month
Created
7
5
0
I have established a baseline summary schedule that uses level of effort activities to monitor progress.
But, when I make a copy of the baseline, and start entering progress on the copy, the progress copy will not show the bars for the baseline activities.
I’ve already checked my bar settings, and the ’primary baseline’ one is turned on.
Any suggestions?

7 replies

Oldest first
  1. 0
    Trevor Wilson ·
    This sounds too easy , but have you checked the position of the bar and that the row height is sufficient.
  2. 0
    Robert Adams ·
    The bars are ’turned on’ , as you suggested, the issue seems to be that if you change an activity from a ’task’ to a ’level of effort’ activity, the baseline bar disappears.
    Try it out - it’s very frustrating!
  3. 0
    Steven Oliver ·
    Try including LOE type activities in the bar filter.


    HTH
  4. 0
    Robert Adams ·
    Yes, that does it - thanks very much!
  5. 0
    Steven Oliver ·
    No problem.
  6. 0
    Sunshine Khesti ·

    Hi, did anyone find the

    Hi, did anyone find the solution to the baseline Level Of Effort not showing bars. Kindly assist

  7. 0
    Raymund de Laza ·

    Try Reading below and follow

    Try Reading below and follow the suggestions, it was solved.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?