Baseline budget and primary baseline

Dinesh Kumar DamavarapuMember for 24 years 7 months
Created
11
4
0
Dear experts, I have two schedules of a same project. One is the original baseline and the other is the revised. some of the activties from the original schedule have been deleted in the revised schedule.When we set the original baseline as primary baseline to the revised schedule,baseline budget figure only reflects the figures related to the activties in the revised schedule but not the total budget in the primary baseline.Is there any option in P3e to show the total budget when set as the primary baseline. Sorry if it is a silly question (I am new to P3e) Your kind advice will be highly appreciated. Thanks & regards Dinesh

11 replies

Oldest first
  1. 0
    Alex Wong ·
    Dinesh

    Unless you still have the original activities that contain the budget in your new program, otherwise you cannot includes and display your original budget correctly.

    In this case, is it mean that your new plan use less than the original budget. What happen to the deleted activities, are they completed or redefine as other activities. You must be very careful when deleting activities.

    To revise it you can copy across the original activity that is still exist in the baseline and reset their budget and remaining.

    Hope it help. When you dealing with baseline be very careful with your budget $ Q and $ Q @ completion

    Alex
  2. 0
    Dayanidhi Dhandapany ·
    Dear Alex,

    I am also a newbie to this Primavera enterprise forum. I would like to know the difference between Primavera Project Planner Professional (shall we call it as P4??) and P3 Enterprise or P4 and P3e are the same product???.

    Cheers!!!

    Daya
  3. 0
    Alex Wong ·
    Daya

    To my knowledge, what you mentioned is the same product. Few differents are
    1. Color (their menu color and look are different)
    2. Standard Report Layout
    3. Field Names (Plan/Budget)

    Beside the above, I do believe they are the same.

    Regards

    Alex
  4. 0
    Dayanidhi Dhandapany ·
    Dear Alex,

    Thank you for clarifying it.

    Cheers!!!

    Daya
  5. 0
    Dinesh Kumar Damavarapu ·
    Hi Alex,

    Thank you for your reply.

    One more question,how can I just import the progress data like actual start, actual finish and percentage complete from the updated programme to the existing programme in the P3e.I used to do that in P3 using exporting and importing between MS Excel and P3.

    Thanks & regards

    Dinesh
  6. 0
    Henk van der Heide ·
    Dear Dinesh

    You can use the SDK (Software Development Kid). In combination with Excel. There’s a spreadsheet called Activity.xls that makes it (simply) possible to commumicate with your database (imput and export) However it stil isn’t as strong as P3, import/export function (for now)


    Regards

    Henk
  7. 0
    Alex Wong ·
    Dear Planner,

    There are tools that utilised SDK and ease the process of importing and exporting in P3e.

    Cheers

    Alex
  8. 0
    Dinesh Kumar Damavarapu ·
    Ofcourse Mr.Alex,I understand you can do that using SDK.do you have any tools or files that you can share with us.

    I also heard we can use access database to link with P3e database and do the neccessary manupulation, has anybody tried it and have any advice.

    Thank you

    Dinesh
  9. 0
    Dayanidhi Dhandapany ·
    Dear Alex,

    I could notice that some of a few simple things just like moving into next years in the Calendars by clicking ">>" buttons are missing in P4. I could not find it as such in P3. Do you know what is the reason of omitting this option in P4.

    Regards

    Daya
  10. 0
    Henk van der Heide ·
    Dear Daynanidhy.

    Clicking to the next year is still very simple.
    When you’re in the calander.
    First click in the month in the calander on the top.Then days will become months, and month becomes year, in the calander. You can click to the next year in one click by the ">" button next to the year.

    Regards

    Henk
  11. 0
    Alex Wong ·
    Dinesh

    Try to search a company call SunTech in Australia

    I think they have a very good product to interface with SDK and P3e.


    Daya

    My problem with the time display in P3e is: it do not have year by year in the resource and time line display. I hate this, because I have to sum the four quarters in order to have th actual annual figures. It is not very good

    Cheers

    Alex

Log in or join to reply