"SS+Lag" or "FF"

Nozar NaghaniMember for 22 years 3 months
Created
3
1
0
Hello
Each project manager prefers to see parallel tasks instead of long chains of FS linked tasks.
Especially when tasks are not very small deliverables, there is always the choice to choose SS+Lag or FF instead of FS relationship.
Example: Instead of waiting for AFC foundation drawing, Structural design can start almost a week after start of foundation design (when calculations are available).
I always wonder which link is the best for this purpose (SS+Lag or FF).

What is your experience?


Have fun

Nozar

3 replies

Oldest first
  1. 0
    Steven Oliver ·
    My preference would be FF, as the start of the successor is then dicated by the progress of the predecessor.


  2. 0
    Nozar Naghani ·
    Hey Steven,
    Thanks for your response.
    In FF case, the successor task will be planned to start latest possible. Task A= 10 days, Task B=2 days. Defining B as successor to A with FF relationship, will plan B to start on day 8, which is not very favorable.
    Am I right?

    Nozar
  3. 0
    Steven Oliver ·
    It should start on day 9 (i.e a 2 day task will occupy days 9&10 to finish coincident with a 10 day activity.

    What makes you think that this would be unfavourable ?

Log in or join to reply