7 days/week calendar

Nozar NaghaniMember for 22 years 3 months
Created
5
2
0
Is this practical to choose "7 days/week calendar" for all tasks and then choose "5 days/week calendar" for labor resources?
Anybody tried it?
Does anybody like to share his/her hands-on experience?

Thanks
Nozar

5 replies

Oldest first
  1. 0
    Puneet Gupta ·
    Yes this is practical for those activities in which 2 nos of labour resource are working ...say 1 resource has 5 day week cal and other resource has 2 day week calendar
  2. 0
    Amar Aghana ·
    I need to set calendars as 5 days a week and week starting as Saturday. How to set this in P3 e&c? (Only soft answers are appreciated!)
  3. 0
    Amar Aghana ·
    I Understood setting week off by workweeks. But how to make week starting as "Saturday"
  4. 0
    Niek Zonneveld ·
    Under [admin] [admin preferences] [general].

    HTH

    Niek.
  5. 0
    Amar Aghana ·
    Thanks, It worked.