Reporting!!!!

Ahu GucluMember for 21 years 5 months
Created
4
4
0
Hello,

In P3EC while reporting resourses,
organized by wbs,
if i want to summary the report ,
"unit/price" and "unit of measure" columns is being blank. i really don’ t understand why it can not summary resourses under wbs with unit of measure and unit/price, because these reasourses are the same.
it just show these columns when all resourses list even if they are the same.
Is there another way to do that???

4 replies

Oldest first
  1. 0
    Bill McMichael ·
    Resource unit of measureable is not summable. It is a text field. I guess it may make sense to show it if as in your case all of the values are identical. There is not a way to do this.

    As far as UPT, again this is not a summable field for a resource assignment. You would not want to simply add the values as this is a ratio.

    You would need to create a report outside of p3e/c’s report writer to do this.

    Regards,
    Bill
  2. 0
    Bill McMichael ·
    Misread part of the question. Unit price is also a non summable. I am not sure how you would want this summarized. I don’t think you would want the values added together.

    Regards,
    Bill
  3. 0
    Ahu Guclu ·
    because i choose the same resourses to the activities,i supposed that the program knows it and may not summarize the valuses but show the the value of UP and UM at the high level.

    THANK YOU
  4. 0
    Henk van der Heide ·
    Ahu,

    The thing is you have to use costs to summarize !!

    Here’s the thing. If you want to summarize for example for earned value proposal than you have to (or better) use costs. What you can do is give each resource a standard cost of 1$/hr. Than costs are equal to units. Make sure that costs units linked is on on activity (resource) level



    Regards

    Henk