Currencies
In the Open Standard
Jihad DanielMember for 21 years 5 months
- Created
- 2
- 2
0
Dear Colleagues,
Working on several projects’ schedules in different countries oblige us to use different currencies. In order to have a project currency set for each project depending on the country or sometimes to have different curencies in the same schedule, what do you suggest to do in both cases?
I created a user defined field – type currency (from menu [Enterprise][User defined Field]) at the activity level. Run a global change to copy costs (Budgeted cost of an activity to the user defined field created). I added another column showing only the currency. We can therefore show two columns, one showing the cost without currency and the other the currency for each activity or each Project. Is this the only way to resolve this issue?
Regards,
J. Daniel
Working on several projects’ schedules in different countries oblige us to use different currencies. In order to have a project currency set for each project depending on the country or sometimes to have different curencies in the same schedule, what do you suggest to do in both cases?
I created a user defined field – type currency (from menu [Enterprise][User defined Field]) at the activity level. Run a global change to copy costs (Budgeted cost of an activity to the user defined field created). I added another column showing only the currency. We can therefore show two columns, one showing the cost without currency and the other the currency for each activity or each Project. Is this the only way to resolve this issue?
Regards,
J. Daniel
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?