Currencies

Jihad DanielMember for 21 years 5 months
Created
2
2
0
Dear Colleagues,

Working on several projects’ schedules in different countries oblige us to use different currencies. In order to have a project currency set for each project depending on the country or sometimes to have different curencies in the same schedule, what do you suggest to do in both cases?

I created a user defined field – type currency (from menu [Enterprise][User defined Field]) at the activity level. Run a global change to copy costs (Budgeted cost of an activity to the user defined field created). I added another column showing only the currency. We can therefore show two columns, one showing the cost without currency and the other the currency for each activity or each Project. Is this the only way to resolve this issue?

Regards,
J. Daniel





2 replies

Oldest first
  1. 0
    Puneet Gupta ·
    Have you used Viewing Currency option?
    Using this you can view any currency in the required currency format (exchange rate need to be set)
  2. 0
    Jihad Daniel ·
    Dear Puneet,

    I tried different options (including viewing currency option, etc.) but I found that the only way to solve this issue is as described in my first message. Please elaborate more if you have any other suggestions.

    Thanks & Regards,
    J. Daniel