Checking predecessor

Nozar NaghaniMember for 22 years 3 months
Created
2
3
0
Hello planners,
Lets see who knows how to:

Create a filter to find completed activities, which their predecessor/s is not yet complete.


Probably we need to do something more than a filter.


Have fun

Nozar Naghani

2 replies

Oldest first
  1. 0
    Jihad Daniel ·
    Simply check scheduling report which will list the activities completed or started and their predecessors did not start yet...It is not complicated at all...

    Regards,
    J. Daniel
  2. 0
    Alex Wong ·
    The best way I can think of is export the complete activity list in a excel table and run a VLookup in the activity list that look up the predecessor actual finish date. Run a auto filter to filter your specified conditions.

    Export the activity id list

    Create a Activity Code

    Import the activity ID + A Special Code

    Filter the code

    I think it is a 5 min job

    Cheers

    Alex