Summary bar colors

Carlos OrtegaMember for 21 years
Created
1
1
0
Is there a way of being able to color different levels of summary bars in different colors?
Like having different levels of WBS summaries bars, each level in a different color?

1 reply

Oldest first
  1. 0
    Steven Oliver ·
    Code each specific level, then use a filter based on these value in the specication for the summary bar.


    HTH

Log in or join to reply