Dear All,

Can we use global change to add common resources to all activities? The same thing we are doing in P3.

I hope that my inquiry be enlightened.

2 replies

Oldest first
  1. 0
    Bill McMichael ·
    Ruel,

    The easiest way to assign one or multiple resources to multiple activities is to use the " Assign Resources" dialog which is accessed by the Resources Button on the Command bar. It will assign resources to selected or highlighted activities. Combine with an activity filter if the assignment needs to meet a selection criteria.

    Regards,
    Bill
  2. 0
    Ruel Llegado ·
    Bill,

    Thank you for the support. I did follow your suggestion and it works.