RE: UPT

Rashid IqbalMember for 21 years 5 months
Created
2
1
0
Hi,

P3 made our Project Managers used to see the no of equipement i.e Truck, Dozers etc right under the Bar Chart. Now with this P3e/c i am unable to show the peak(UPT) of each resource in the resource spreadsheet. I have tried ’average’ but it is quite deceptive and is not producing the same results.

I was wondering if someone might have found some way around.

2 replies

Oldest first
  1. 0
    David Kelly ·
    The fact that P3 allowed "total, peak or average" in the resource table view and P3e only allows "total or average" in the resource spreadsheet has been a problem I have wrestled with for a couple of years now. I’ve no work around, and I have contact with a lot of clients who would have used any work arounnd they could find.
  2. 0
    Rashid Iqbal ·
    Thanks for your reply and it was a pleasure to learn that there is someone else also who is missing this function.

    Regards
    Rashid Iqbal