Dear all,

A frined of mine has this doubt:

Can Duration%Complete (for Activity progress) be different of Units%Complete (for Resource progress on activity)??

In my opinion, it can be different. Activity progress can be proportionally different of Resource progress. By the way, it normally happens.

Any different opinion??

Regards,

Marcio Eduardo.
Rio de Janeiro - Brazil.

2 replies

Oldest first
  1. 0
    Kevin Button ·
    Marcio

    It certainly is possible (and often necessary) to have Duration % and Units % working independently. In project view, select the Calculations tab and make sure the box titled "Recalculate Actual Units and Cost when duration % complete changes" is NOT ticked.

    You will still need to define a suitable default % complete type for your activities (either duration, units or physical) but you can display the columns for each of these % types in the activity view.

    Regards
  2. 0
    Marcio Sampaio ·
    Kevin,

    Thanks for your interest.

    Best regards.

    Marcio Eduardo
    Rio de Janeiro - Brazil.