Primavera V4.1 - Show % in Total
In the Open Standard
BC
Brian CameronMember for 22 years 5 months
- Created
- 10
- 2
0
Is it possible to show the overall % complete at the top of a project?
Similar to the way that MS Project rolls up the percentages from the various levels.
I have the "Show Grand Totals" ticked in "Group and Sort" which shows all the essential information with the exception of an overall percentage for the project.
Any ideas?
Regards
Brian.
Similar to the way that MS Project rolls up the percentages from the various levels.
I have the "Show Grand Totals" ticked in "Group and Sort" which shows all the essential information with the exception of an overall percentage for the project.
Any ideas?
Regards
Brian.
10 replies
Oldest first- 0PHPaul Harris ·Brian
You need to show the appropriate column to get a summary percent complete. The Duration % Complete, Units % Complete and Cost % Complete will usually show different values.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au
- 0DKDavid Kelly ·WOW, such a big topic in P3e, Percent Complete and how to roll it up. I run a half day workshop for expert users on the subject. In summary:
1) if you do not use resources, use "Duration percent complete"
2) If you use resources, and they are all priced (if you do not use resource unit prices, set them all to 1.00) then use "performance per cent complete"
- 0BCBrian Cameron ·Hi Dave
I tried Paul Harris’s ideas and I didn’t get what I wanted, probably because of a few things I have not set up correctly!
What I have set up doesn’t fit your two solutions.
The best bet is I give you an idea of what I have.
The project defaults are set as fixed duration and units, percent complete type physical, and resource dependent.
The general information about the activities are that they are resource dependent, fixed duration and units and physical percent complete type.
Resources are set at 8hr/dy and are unpriced, because time collection and finance is controlled through another system.
Basically just a activities in a WBS layout linked together with durations, hours and resources.
Any ideas ?
Regards
Brian. - 0BCBrian Cameron ·Alex
The solution was a combination of showing the duration % column, progressing the schedule and having the totals selected in the group and sort.
When all of those were applied the information was visible.
This was on a new schedule and I hadn’t scheduled it after entering the first progress collected(asked not to by others!!), so things weren’t behaving as I expected.
Thanks for your reply.
Brian.
- 0JTJorge Taguinod ·Hi Brian,
I’m not sure if your "project" is actually a program (a collection of projects) in Primavera. If so, then I’ll just tackle a WBS.
Let’s assume that a WBS is actually a Work Package that is contracted out, and therefore is a project in itself.
Let’s also assume that you measure progress for this WBS by Physical Percent Complete.
The reason for these assumptions is that if you’re inquiring about the total percent complete of a group of projects, each using different bases of progress measurements (duration, physical, etc.) then there’d be a lot lot more discussion on how to valuate these different activities.
So going back to the Work Package, if actities are costed (via using resources that have unit prices OR by loading expenses as reflected in the contract document), and you set the measurement of all activities in the WBS to Physical Percent Complete, then by displaying Activity Percent Complete in the Column, Primavera can give you a Total Percent Complete for that specific WBS.
This is because it is comparing apples to apples. It uses Earned Value to come up with your WBS Percent Complete.
Now, if you have another Work Package that is duration-based for progress measurement, Primavera will simply use the total of that WBS as the total number of work periods used as the basis for your Activity Percent Complete, and consequently for the WBS Percent Complete.
However: Please check also the settings for WBS earned value.
The problem lies in asking Primavera what is the total percent complete of the whole program (if you used WBS to contain each project). How does Primavera weigh a duration-based activity with no costs (resource or expenses) with a physical-based activity (which are costed?).
Also, for a long-term program where some Work Packages are still being planned (no budget), while others are already being executed and others are already closed out: How will Primavera (or any other software, for that matter) give you a "Project" percent complete.
This is the reason i focused on a single Work Package (WBS Node).
Hope this helps.
Best regards,
Jorge - 0HMHazel Mendez ·Hello,
Is it possible to define weight value code on "custom data items" and add weight value for each activities and show percent complete based on this weight value? I’m not sure if "custom data item" function is available in P3 e/c.
Your reply to this matter will be highly appreciated. Thank you.
hazel - 0AWAlex Wong ·Hazel
The answer is yes and no
Yes - P3e do have CDI (what they call now is user define field
Yes it can calculate base on a activities level where the basic calculation is allow (No global change needed) (ONLY in Version 5)
No you cannot just adding the % together. because each summary level is different. As a result, it cannot work out CPI SPI at a summary by using CDI/UDF
Therefore, the two options are
1 use the standard EV calculated function in P3e
2 use the UDF and export to excel to calculate EV
HTH
Alex