Help needed-Importing MSP to Ver.5

Suraj BhattMember for 22 years 4 months
Created
3
3
0
Hi all!
I am having problem in importing a MSP schedule into Primavera Ver.5.
I have imported the file but as soon as I schedule it in Ver.5 the dates change.Also all the activities that were task dependent in MSP have become resource dependent after importing in Ver.5.
Before importing I selected all the activities and removed "Effort driven". I cleared the baseline too.

Regards,
Suraj

3 replies

Oldest first
  1. 0
    Marcio Sampaio ·
    Suraj Bhatt;

    Too many things can be causing this problem.

    Calendars, lags, relathionships, durations etc.

    I suggest u to check all this topics in all activities and try to find what is wrong.

    Good luck.
  2. 0
    Suraj Bhatt ·
    Well thanks!
    I solved the dates problem.They match now but why did the activities became resource dependent???
    Suraj
  3. 0
    Marcio Sampaio ·
    I understand that it is a default of Primavera - import activities as resource dependent - I never knew a place where I could configure this.
    I dont know if it’s diferent in P5, maybe some other PP member could tel us.
    By the way it is easy to change this using fill down.

    Regards.

    Marcio Eduardo

Log in or join to reply