P5 database

Gordon BennettMember for 22 years 11 months
Created
1
3
0
In P3E 4.1 I used to back up the whole PMDB.GDB database, but in version 5 the database is hidden. Can I back up the whole database in this version or is it only XER file backups for individual projects ?

1 reply

Oldest first
  1. 0
    Joao Ribeiro ·
    If P5 just works with MSSQL or Oracle databases, you should look for *.MDF (database) and *.LDF (log) files and backup them.
    The extensions MDF and LDF are MSSQL. For Oracle you will have to find out.

    Hope this is correct and helps you.