Assign wbs codes fast

Panayiotis Alan ageMember for 17 years 10 months
Created
5
4
0
Can you please advise me a way to assign wbs codes for group of activities, without the necessity of doing this for each activity?

5 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Alan,

    Welcome to Planning Planet.

    You can display the WBS & Activity Code in your Column and use the Fill down (CTRL+E). Or you can even drag/move the activities to the WBS level.

    Another thing is, try to export to excel and assign it.

    HTH.

    Regards,

    Arnold
  2. 0
    Panayiotis Alan age ·
    You are very correct. Thank you very much
  3. 0
    Arnold Puy ·

    You are welcome.

  4. 0
    David Wallace ·
    Can you use ’RA’ files in P5/P6?

    If you can why don’t you export the WBS dictionery skeleton to the PROJECT.xls file, fill it out quickly in Excel and then re-import it?

    David.
  5. 0
    Arnold Puy ·
    Hi Mr. David,

    If I’m not mistaken, you can’t. "RA" is similar to "SDK" in P3. There is a Dictionary6x for P6. However, there is no WBS in here, only Activity Codes.

    There is one more called "PATTLNK_632006_536-xerFileParser&Builder" but a little bit difficult to assign the WBS & Activity Code.

    Regards,

    Arnold