WBS calendar

Marcio SampaioMember for 20 years 11 months
Created
9
1
0
Dear all,

Why do sometimes a wbs level duration is diferent than its total activities duration??

I have a small shcedulle, only onde calendar (for project and activities) and this conflit is happening.

Which calendar wbs cosider?? Is it "time periods" defined in Admin Preferences??

Regards.

9 replies

Oldest first
  1. 0
    Niek Zonneveld ·
    PRIM2849:

    The original duration in the WBS summary bands is calculated as the following:

    Latest Planned Finish - The Earliest Planned Start.

    Project Manager uses the default Global calendar to determine the number of timeperiods based on the above calculation.

    ********************

    This means that if your project calendar and the default global calendar are not the same, you can have deviations.

    Hope this helps,

    Niek.
  2. 0
    Marcio Sampaio ·
    Thanks a lot Niek.
  3. 0
    Marcio Sampaio ·
    Niek,

    I’m working with P3e ... is it still happening in P5??

    Regards.
  4. 0
    Niek Zonneveld ·
    Yep that’s the case.

    I don’t see how it could work any other way, because how would you treat grouped activities with multiple calendars? (not just by WBS, but also any other (combined) grouping)

    H.T.H.
  5. 0
    Marcio Sampaio ·
    I understand and i’m agree.

    But I think that the ideal should be P5 to allows user to choose which calendar wbs consider.

    Regards.
  6. 0
    Marcio Sampaio ·
    I understand and i’m agree.

    But I think that the ideal should be P5 to allows user to choose which calendar wbs consider.

    Regards.
  7. 0
    Marcio Sampaio ·
    Do u think it is possible for next release??
  8. 0
    Kevin Button ·
    I think it’s a good idea, send email to primavera with this enhancement request and they will put it on the list.

    Cheers
  9. 0
    Marcio Sampaio ·
    Ok Kevin ... i’m sending it.

    Thanks and regards.