John StevensonMember for 23 years
Created
2
1
0
when adding volumes in p3e how can i report on systems per year ... 1 ea/y what is the correct way of defining this as i would like a report on volumes/systems per month also

2 replies

Oldest first
  1. 0
    John Stevenson ·
    i have added the volume via resource
  2. 0
    John Stevenson ·
    worked this one out,
    budgeted units/ systems 1
    actual units/ systems 1
    remaining units/ systems 0

    this can be applied to all or any commissioning or site works/deliverables and or plant/spares...