Converting MS Project Expenses to Contractor Resources?

Tim GibsonMember for 20 years 5 months
Created
1
2
0
I am importing a consultant’s MS Project schedule into Primavera Contractor. The costs for each activity import into "expenses." I need to convert the expenses into resources so I can run resource reports.

Contractor won’t import/export to a spreadsheet, so I can’t do it that way.

Any ideas?

Thanks!

1 reply

Oldest first
  1. 0
    Marcio Sampaio ·
    I’m not sure, but i think it is not possible in a conversion MS Project to Contractor. U will have to do it manually.

    Regards.