BL Cost % Complete - Summary Roll-up
In the Open Standard
Amir DadbakhshMember for 22 years
- Created
- 6
- 2
0
Dear Planner
I’ve faced a problem, I would be really glad if you help me to solve it.
I should compare actual time schedule with baseline time schedule, my problem is:
in "BL Cost % Complete", cost % complete is not roll up for summary activity (in WBS level, it doesn’t show total) even I restored the baseline it worked well and all cost % complete was rollup but when I mark it as baseline again it is not roll up in summary level (total was not shown!)
I’ve tried many ways such as changing data date,… but they couldn’t help me!
How can I make primavera sums and shows total cost % complete in "BL cost % complete" for summary task?
Thanks in advance
Amir
I’ve faced a problem, I would be really glad if you help me to solve it.
I should compare actual time schedule with baseline time schedule, my problem is:
in "BL Cost % Complete", cost % complete is not roll up for summary activity (in WBS level, it doesn’t show total) even I restored the baseline it worked well and all cost % complete was rollup but when I mark it as baseline again it is not roll up in summary level (total was not shown!)
I’ve tried many ways such as changing data date,… but they couldn’t help me!
How can I make primavera sums and shows total cost % complete in "BL cost % complete" for summary task?
Thanks in advance
Amir
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?