Skip to content

Overall Physical %

Rabbani WglMember for 20 years 5 months
Created
5
3
0
Hello Experts,
Can you please tell how to show overall Physical% complete for a project in P3 e/c... the way it shows when the % complete type is Duration % Complete.

Thanks
Rabbani

5 replies

Oldest first
  1. 0
    Marcio Sampaio ·
    Hello Habbani;

    Try to see what i wrote on BL Cost % Complete - Summary Roll-up here in Primavera Enterprise - Teamplay / P3e & P3ec category.

    http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=8&Top=21607

    Hope it helps.

    Regards.

    Marcio Eduardo
  2. 0
    Julie Scully ·
    Summarising the physical % complete is currently an enhancement request that Primavera are looking into. They have a workaround on the knowledgebase (bulletin # prim11292), but one of the conditions is having costs assigned to the activities.

    HTH

    Cheers
    Julie
  3. 0
    Marcio Sampaio ·
    Heelo Julie,

    Do u know why Costs assingned is a condition? Why not units only?

    Regards.
  4. 0
    Julie Scully ·
    Marcio

    From the bulletin...

    "At the summary level, the Performance % complete is calculated as follows:

    Performance % Complete = (BCWP * 100) / BAC

    (Where the BCWP is the Budgeted Cost of Work Performed and the BAC is the Budget At Completion)

    BCWP is calculated as Activity % Complete * Baseline Total Cost"


    Cheers
    Julie

  5. 0
    Marcio Sampaio ·
    Thanks Julie,

    Now it is clear to me.

    Regards.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?